Villa Aurora
Location : Jalan Mertanadi, Kerobokan, Bali
Client : Rizal Pickard
Architect : Owner.
- Bali villa building – construction work
- Bali villa building – construction work
- Bali villa building – construction work
- Bali villa building – construction work
- Bali villa building – construction work
- Construction work cooperation contract signing 02.09.2021
- Arranging project financing with banks
- Construction work preparation
- Land ready and construction work to start soon
- Land ready and construction work to start soon
- Start bowplank
- Start bowplank
- Start bowplank
- Start bowplank
- Main entrance
- Main entrance
- Main entrance
- Main entrance
- Preparation of backfill work
- Preparation of backfill work
- Preparation of backfill work
- Preparation of backfill work
- Backfill work
- Backfill work
- Backfill work
- Backfill work
- Backfill work
- Backfill work
- Land boundary fence work
- Site preparation
- Site preparation
- Site preparation
- Site is ready for contruction activities
- Site is ready for contruction activities
- Bored Pile : Foundations for the construction of a building are generally divided into two types, namely shallow foundations and deep foundations. Bored pile is one type of deep foundation which can be used as another alternative if in the implementation of foundation making it is not possible to use a spoon pile foundation.
- Bored Pile : Foundations for the construction of a building are generally divided into two types, namely shallow foundations and deep foundations. Bored pile is one type of deep foundation which can be used as another alternative if in the implementation of foundation making it is not possible to use a spoon pile foundation.
- Bored Pile : Foundations for the construction of a building are generally divided into two types, namely shallow foundations and deep foundations. Bored pile is one type of deep foundation which can be used as another alternative if in the implementation of foundation making it is not possible to use a spoon pile foundation.
- Floor work is a job that is usually done in building construction with a fairly complex scope and environmental conditions. The working floor thickness is usually 10-15 cm thick. The functions of making a work floor are as follows: Makes it easier for workers to stand on flat land, the land is not dirty and muddy. It is an under-layer iron mount (for raft or pile-cap foundations. Withstands the up-lift force of the ground beneath it.
- Floor work is a job that is usually done in building construction with a fairly complex scope and environmental conditions. The working floor thickness is usually 10-15 cm thick. The functions of making a work floor are as follows: Makes it easier for workers to stand on flat land, the land is not dirty and muddy. It is an under-layer iron mount (for raft or pile-cap foundations. Withstands the up-lift force of the ground beneath it.
- Floor work is a job that is usually done in building construction with a fairly complex scope and environmental conditions. The working floor thickness is usually 10-15 cm thick. The functions of making a work floor are as follows: Makes it easier for workers to stand on flat land, the land is not dirty and muddy. It is an under-layer iron mount (for raft or pile-cap foundations. Withstands the up-lift force of the ground beneath it.
- Floor work is a job that is usually done in building construction with a fairly complex scope and environmental conditions. The working floor thickness is usually 10-15 cm thick. The functions of making a work floor are as follows: Makes it easier for workers to stand on flat land, the land is not dirty and muddy. It is an under-layer iron mount (for raft or pile-cap foundations. Withstands the up-lift force of the ground beneath it.
- Pile cap is used as a foundation to bind the piles that have been installed with the structure above it. The purpose of making a pile cap is so that the location of the column is really at the center of the foundation so that it does not cause eccentricity which can cause additional loads on the foundation.
- Pile cap is used as a foundation to bind the piles that have been installed with the structure above it. The purpose of making a pile cap is so that the location of the column is really at the center of the foundation so that it does not cause eccentricity which can cause additional loads on the foundation.
- Pile cap is used as a foundation to bind the piles that have been installed with the structure above it. The purpose of making a pile cap is so that the location of the column is really at the center of the foundation so that it does not cause eccentricity which can cause additional loads on the foundation.
- Laim stone fill before lean concrete
- Laim stone fill before lean concrete
- Lean concrete or called LC is a work floor for rigid pavement work. So this layer is not a structural layer. However, it must be present before concrete work (rigid). Its function is only as a work floor so that cement water does not seep into the bottom layer.
- Lean concrete or called LC is a work floor for rigid pavement work. So this layer is not a structural layer. However, it must be present before concrete work (rigid). Its function is only as a work floor so that cement water does not seep into the bottom layer.
- Progress 20%
- Progress 20%
- Progress 20%
- Progress 20%
- Progress 20%
- Progress 20%
- Progress 20%
- Progress 20%
- Progress 20%
- Progress 20%
- Progress 20%
- Tie beam is a structural element found in buildings or buildings that use deep foundations or local shallow foundations. This tie beam is located above ground and on local shallow foundations such as footplate foundations or deep foundations
- Completion of installation of tie beams
- Mill test certificate or iron certification from the factory is a document that guarantees product quality in the metal industry and is issued by the manufacturer’s factory. The function of this document is to certify the physical and chemical properties of a material
- Mill test certificate or iron certification from the factory is a document that guarantees product quality in the metal industry and is issued by the manufacturer’s factory. The function of this document is to certify the physical and chemical properties of a material
- Completion of installation of tie beams
- Completion of installation of tie beams
- Tie beams are ready in place, then the ground floor concrete casting stage uses the K-250 specification
- Tie beams are ready in place, then the ground floor concrete casting stage uses the K-250 specification
- Tie beams are ready in place, then the ground floor concrete casting stage uses the K-250 specification
- Tie beams are ready in place, then the ground floor concrete casting stage uses the K-250 specification
- Tie beams are ready in place, then the ground floor concrete casting stage uses the K-250 specification
- Tie beams are ready in place, then the ground floor concrete casting stage uses the K-250 specification
- Tie beams are ready in place, then the ground floor concrete casting stage uses the K-250 specification
- Tie beams are ready in place, then the ground floor concrete casting stage uses the K-250 specification
- Always monitor the availability of materials, the quality of the materials used, and provide quality workforces
- Always monitor the availability of materials, the quality of the materials used, and provide quality workforces
- Always monitor the availability of materials, the quality of the materials used, and provide quality workforces
- Always monitor the availability of materials, the quality of the materials used, and provide quality workforces
- Preparation of concrete casting on the ground floor slab using ready mix K250
- Preparation of concrete casting on the ground floor slab using ready mix K250
- Preparation of concrete casting on the ground floor slab using ready mix K250
- Preparation of concrete casting on the ground floor slab using ready mix K250
- Preparation of concrete casting on the ground floor slab using ready mix K250
- Concrete Quality K250 is a quality concrete that has a compressive strength of up to 250 kilograms per square meter. … the middle class is usually used for the manufacture of columns, foundations and sloof. In addition, structural construction, such as concrete cyclops, sidewalks and bridges.
- The manufacture of concrete cylinders is as a replication of the concrete used for building materials. This concrete cylinder is made from the concrete mix that will be used, which is a sample that will be tested in the laboratory. The number of making concrete cylinders must be presented from the concrete mix of building materials.
- The manufacture of concrete cylinders is as a replication of the concrete used for building materials. This concrete cylinder is made from the concrete mix that will be used, which is a sample that will be tested in the laboratory. The number of making concrete cylinders must be presented from the concrete mix of building materials.
- The manufacture of concrete cylinders is as a replication of the concrete used for building materials. This concrete cylinder is made from the concrete mix that will be used, which is a sample that will be tested in the laboratory. The number of making concrete cylinders must be presented from the concrete mix of building materials.
- The implementation of casting concrete is carried out after the installation of formwork and reinforcement is complete, in this case the casting is carried out simultaneously so that it will speed up time. Pouring concrete species into concrete slab using pump concentrate and in this implementation we use ready mix concrete with K 250
- The implementation of casting concrete is carried out after the installation of formwork and reinforcement is complete, in this case the casting is carried out simultaneously so that it will speed up time. Pouring concrete species into concrete slab using pump concentrate and in this implementation we use ready mix concrete with K 250
- The implementation of casting concrete is carried out after the installation of formwork and reinforcement is complete, in this case the casting is carried out simultaneously so that it will speed up time. Pouring concrete species into concrete slab using pump concentrate and in this implementation we use ready mix concrete with K 250
- The implementation of casting concrete is carried out after the installation of formwork and reinforcement is complete, in this case the casting is carried out simultaneously so that it will speed up time. Pouring concrete species into concrete slab using pump concentrate and in this implementation we use ready mix concrete with K 250
- The implementation of casting concrete is carried out after the installation of formwork and reinforcement is complete, in this case the casting is carried out simultaneously so that it will speed up time. Pouring concrete species into concrete slab using pump concentrate and in this implementation we use ready mix concrete with K 250
- My self, Teguh (Foreman), and Putu (Site Engineer)
- A special work team for concrete casting work, led by Teguh (Foreman)
- The implementation of casting concrete is carried out after the installation of formwork and reinforcement is complete, in this case the casting is carried out simultaneously so that it will speed up time. Pouring concrete species into concrete slab using pump concentrate and in this implementation we use ready mix concrete with K 250
- Need overtime because the concrete casting work must be completed in one time without a break.
- Need overtime because the concrete casting work must be completed in one time without a break.
- The ground floor slab concrete casting has been completed with satisfactory results
- The ground floor slab concrete casting has been completed with satisfactory results
- Checking verticality during preparation of column formwork installation in order to maintain load transfer between levels of multi-story building structures.
- Checking verticality during preparation of column formwork installation in order to maintain load transfer between levels of multi-story building structures.
- Checking verticality during preparation of column formwork installation in order to maintain load transfer between levels of multi-story building structures.
- SK SNI T-15-1991-03 defines a column as a structural component of a building whose main task is to support vertical compressive axial loads with an unsupported height of at least three times the smallest lateral dimension. ️ Ground floor : 35×35 cm
- SK SNI T-15-1991-03 defines a column as a structural component of a building whose main task is to support vertical compressive axial loads with an unsupported height of at least three times the smallest lateral dimension. ️ Ground floor : 35×35 cm
- SK SNI T-15-1991-03 defines a column as a structural component of a building whose main task is to support vertical compressive axial loads with an unsupported height of at least three times the smallest lateral dimension. ️ Ground floor : 35×35 cm
- SK SNI T-15-1991-03 defines a column as a structural component of a building whose main task is to support vertical compressive axial loads with an unsupported height of at least three times the smallest lateral dimension. ️ Ground floor : 35×35 cm
- SK SNI T-15-1991-03 defines a column as a structural component of a building whose main task is to support vertical compressive axial loads with an unsupported height of at least three times the smallest lateral dimension. ️ Ground floor : 35×35 cm
- SK SNI T-15-1991-03 defines a column as a structural component of a building whose main task is to support vertical compressive axial loads with an unsupported height of at least three times the smallest lateral dimension. ️ Ground floor : 35×35 cm
- The manufacture of panels for the sides of the mold or column formwork is supported using wooden beams in an upright direction. This panel is also supported horizontally with horizontal reinforcement in the form of clamps that are adjusted to the plan. The part that needs more attention is how to bring together the panels to form a corner that can meet well. Upright reinforcing beams usually use wooden beams with sizes and spacing based on the plan.
- The manufacture of panels for the sides of the mold or column formwork is supported using wooden beams in an upright direction. This panel is also supported horizontally with horizontal reinforcement in the form of clamps that are adjusted to the plan. The part that needs more attention is how to bring together the panels to form a corner that can meet well. Upright reinforcing beams usually use wooden beams with sizes and spacing based on the plan.
- The manufacture of panels for the sides of the mold or column formwork is supported using wooden beams in an upright direction. This panel is also supported horizontally with horizontal reinforcement in the form of clamps that are adjusted to the plan. The part that needs more attention is how to bring together the panels to form a corner that can meet well. Upright reinforcing beams usually use wooden beams with sizes and spacing based on the plan.
- Final check before placing concrete on the column, using K250.
- Final check before placing concrete on the column, using K250.
- Final check before placing concrete on the column, using K250.
- In this case the required strength concrete design is K-250, the Concrete Design Mix process for a volume of 1m3 for normal concrete method SNI 7394:2008 with a total weight of 2474 Kg obtained for 215 liters of water, 384 Kg cement, 770 Kg fine aggregate, and coarse aggregate 1105 Kg.
- In this case the required strength concrete design is K-250, the Concrete Design Mix process for a volume of 1m3 for normal concrete method SNI 7394:2008 with a total weight of 2474 Kg obtained for 215 liters of water, 384 Kg cement, 770 Kg fine aggregate, and coarse aggregate 1105 Kg.
- The process of completing the 22 columns on the ground floor.
- The process of completing the 22 columns on the ground floor.
- The process of completing the 22 columns on the ground floor.
- GOD bless Hardworkers
- GOD bless Hardworkers
- The process of completing the 22 columns on the ground floor.
- The process of completing the 22 columns on the ground floor.
- The last 4 columns of concrete cast from a total of 22 columns with K250 concrete quality was completed today, according to schedule.
- The last 4 columns of concrete cast from a total of 22 columns with K250 concrete quality was completed today, according to schedule.
- The last 4 columns of concrete cast from a total of 22 columns with K250 concrete quality was completed today, according to schedule.
- 31.12.2021 Ground floor structural work completed.
- 31.12.2021 Ground floor structural work completed.
- 31.12.2021 Ground floor structural work completed.
- Happy New Year 2022
- Scaffolding basically has several benefits. ️The first benefit is as a temporary structure that is used to support loads that have not been able to carry their own weight. Usually used when casting. ️The second benefit is as a temporary structure that is used to assist in the installation of iron or other materials in a construction project. In addition, in terms of function, scaffolding has two functions including functions as support and as access. ️
- Scaffolding basically has several benefits. ️The first benefit is as a temporary structure that is used to support loads that have not been able to carry their own weight. Usually used when casting. ️The second benefit is as a temporary structure that is used to assist in the installation of iron or other materials in a construction project. In addition, in terms of function, scaffolding has two functions including functions as support and as access. ️
- Scaffolding basically has several benefits. ️The first benefit is as a temporary structure that is used to support loads that have not been able to carry their own weight. Usually used when casting. ️The second benefit is as a temporary structure that is used to assist in the installation of iron or other materials in a construction project. In addition, in terms of function, scaffolding has two functions including functions as support and as access. ️
- 1st floor structure work process.
- Swimming pool excavation work
- Swimming pool structure work process
- Swimming pool structure work process
- Swimming pool structure work process
- 1st floor structure work process.
- 1st floor structure work process.
- God bless Hardworkers!
- Swimming pool structure work process
- Swimming pool structure work process
- Swimming pool structure work process
- Swimming pool structure work process
- Swimming pool structure work process
- Swimming pool structure work process
- 1st floor structure work process.
- 1st floor structure work process.
- In addition to using the right material with SNI (Mile Certificate) quality, we also prioritize the neatness of the installation.
- In addition to using the right material with SNI (Mile Certificate) quality, we also prioritize the neatness of the installation.
- In addition to using the right material with SNI (Mile Certificate) quality, we also prioritize the neatness of the installation.
- The results of the concrete cast on the floor and walls of the swimming pool, using the site mixed method, the quality of the concrete is K250.
- The results of the concrete cast on the floor and walls of the swimming pool, using the site mixed method, the quality of the concrete is K250.
- In addition to using the right material with SNI (Mile Certificate) quality, we also prioritize the neatness of the installation.
- In addition to using the right material with SNI (Mile Certificate) quality, we also prioritize the neatness of the installation.
- In addition to using the right material with SNI (Mile Certificate) quality, we also prioritize the neatness of the installation.
- In addition to using the right material with SNI (Mile Certificate) quality, we also prioritize the neatness of the installation.
- In addition to using the right material with SNI (Mile Certificate) quality, we also prioritize the neatness of the installation.
- In addition to using the right material with SNI (Mile Certificate) quality, we also prioritize the neatness of the installation.
- In addition to using the right material with SNI (Mile Certificate) quality, we also prioritize the neatness of the installation.
- In addition to using the right material with SNI (Mile Certificate) quality, we also prioritize the neatness of the installation.
- In addition to using the right material with SNI (Mile Certificate) quality, we also prioritize the neatness of the installation.
- In addition to using the right material with SNI (Mile Certificate) quality, we also prioritize the neatness of the installation.
- First layer warmesh M8 installation
- First layer warmesh M8 installation
- First layer warmesh M8 installation
- First layer warmesh M8 installation
- First layer warmesh M8 installation
- First layer warmesh M8 installation
- First layer warmesh M8 installation
- First layer warmesh M8 installation
- First layer warmesh M8 installation
- First layer warmesh M8 installation
- First layer warmesh M8 installation
- First layer warmesh M8 installation
- Second layer warmesh M8 installation
- Second layer warmesh M8 installation
- Second layer warmesh M8 installation
- Second layer warmesh M8 installation
- Second layer warmesh M8 installation
- Second layer warmesh M8 installation
- Preparation of cast concrete slab first floor K250
- Preparation of cast concrete slab first floor K250
- Preparation of cast concrete slab first floor K250
- The implementation of casting concrete is carried out at the 1st floor after the installation of formwork and reinforcement is complete, in this case the casting is carried out simultaneously so that it will speed up time. Pouring concrete species into concrete slab using pump concentrate and in this implementation we use ready mix concrete with K 250
- The implementation of casting concrete is carried out at the 1st floor after the installation of formwork and reinforcement is complete, in this case the casting is carried out simultaneously so that it will speed up time. Pouring concrete species into concrete slab using pump concentrate and in this implementation we use ready mix concrete with K 250
- The implementation of casting concrete is carried out at the 1st floor after the installation of formwork and reinforcement is complete, in this case the casting is carried out simultaneously so that it will speed up time. Pouring concrete species into concrete slab using pump concentrate and in this implementation we use ready mix concrete with K 250
- Need overtime because the concrete casting work must be completed in one time without a break.
- Need overtime because the concrete casting work must be completed in one time without a break.
- Need overtime because the concrete casting work must be completed in one time without a break.
- Need overtime because the concrete casting work must be completed in one time without a break.
- Repairing areas damaged by mixer truck traffic so as not to cause complaints from neighbors
- Repairing areas damaged by mixer truck traffic so as not to cause complaints from neighbors
- 24.02.2022 Ground floor structural work completed.
- 24.02.2022 Ground floor structural work completed.
- 24.02.2022 Ground floor structural work completed.
- 24.02.2022 Ground floor structural work completed.
- 24.02.2022 Ground floor structural work completed.
- 24.02.2022 Ground floor structural work completed.
- In this case the required strength concrete design is K-250, the Concrete Design Mix process for a volume of 1m3 for normal concrete method SNI 7394:2008 with a total weight of 2474 Kg obtained for 215 liters of water, 384 Kg cement, 770 Kg fine aggregate, and coarse aggregate 1105 Kg.
- In this case the required strength concrete design is K-250, the Concrete Design Mix process for a volume of 1m3 for normal concrete method SNI 7394:2008 with a total weight of 2474 Kg obtained for 215 liters of water, 384 Kg cement, 770 Kg fine aggregate, and coarse aggregate 1105 Kg.
- Checking the results of concrete work and ensuring the quality of the work according to specifications
- Checking the results of concrete work and ensuring the quality of the work according to specifications
- Checking the results of concrete work and ensuring the quality of the work according to specifications
- Checking the results of concrete work and ensuring the quality of the work according to specifications
- Checking the results of concrete work and ensuring the quality of the work according to specifications
- Checking the results of concrete work and ensuring the quality of the work according to specifications
- Checking the results of concrete work and ensuring the quality of the work according to specifications
- The pressure test was carried out in the laboratory of the Faculty of Engineering, Udayana University, to independently determine the quality of the concrete according to specifications.
- The pressure test was carried out in the laboratory of the Faculty of Engineering, Udayana University, to independently determine the quality of the concrete according to specifications.
- The pressure test was carried out in the laboratory of the Faculty of Engineering, Udayana University, to independently determine the quality of the concrete according to specifications.
- Wall installation work on the ground floor
- Wall installation work on the ground floor
- Wall installation work on the ground floor
- Wall installation work on the ground floor
- The pressure test on the swimming pool is carried out to determine whether there is a leak or not in the plumbing installation.
- Wall installation work on the ground floor
- Wall installation work on the ground floor
- Wall installation work on the ground floor
- Wall installation work on the ground floor
- Wall installation work on the ground floor
- Wall installation work on the ground floor
- Rough plastering on the walls on the ground floor.
- Rough plastering on the walls on the ground floor.
- Rough plastering on the walls on the ground floor.
- Rough plastering on the walls on the ground floor.
- Rough plastering on the walls on the ground floor.
- Rough plastering on the walls on the ground floor.
- Rough plastering on the walls on the ground floor.
- Waterproofing on the concrete floor on the first floor
- Waterproofing on the concrete floor on the first floor
- Waterproofing on the concrete floor on the first floor
- Waterproofing on the concrete floor on the first floor
- Steel staircase installation
- Steel staircase installation
- Steel staircase installation
- Steel staircase installation
- Bio septic installation
- Bio septic installation
- Flat roof installation
- Progress 18.04.2022
- Steel staircase installation
- Steel staircase installation
- Steel staircase installation
- Steel staircase installation
- Steel staircase installation
- Steel staircase installation
- Completion of roof work
- Rough plastering on the walls on the ground floor.
- Progress 23.04.2022
- Always monitor the availability of materials, the quality of the materials used, and provide quality workforces
- We provide The Best Quality of Work
- We provide The Best Quality of Work
- Progress 60% 29.04.2022
- Progress 60% 29.04.2022
- Let’s finish what we started. All The Best !
- Preparation of finishing materials and labor to complete all work
- Preparation of finishing materials and labor to complete all work
- Preparation of finishing materials and labor to complete all work
- Preparation of finishing materials and labor to complete all work
- Preparation of finishing materials and labor to complete all work
- Preparation of finishing materials and labor to complete all work
- Inspection by Owner 19.05.2022
- Inspection by Owner 19.05.2022
- Inspection by Owner 19.05.2022
- The owner is satisfied with the work at the 60% progress position
- Swimming pool work process
- Swimming pool work process
- Swimming pool work process
- Swimming pool work process
- Swimming pool work process
- Swimming pool work process
- Swimming pool work process
- Swimming pool work process
- Swimming pool work process
- The process of ceiling installation work is in line with ME . work
- The process of ceiling installation work is in line with ME . work
- The process of ceiling installation work is in line with ME . work
- The process of ceiling installation work is in line with ME . work
- The process of ceiling installation work is in line with ME . work
- The process of ceiling installation work is in line with ME . work
- The process of ceiling installation work is in line with ME . work
- The process of ceiling installation work is in line with ME . work
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Our MEP Engineer loves his job very much
- Our MEP Engineer loves his job very much
- Our MEP Engineer loves his job very much
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Pool pump installation
- Trowel machine, also known as power floats, are tools used during construction to apply a smooth finish to concrete slabs. It is essential to trowel after each concrete pour because this allows the concrete to continue the process of finishing the concrete and squeezing out residual water
- Trowel machine, also known as power floats, are tools used during construction to apply a smooth finish to concrete slabs. It is essential to trowel after each concrete pour because this allows the concrete to continue the process of finishing the concrete and squeezing out residual water
- 03.07.2022
- 04.07.2022
- 04.07.2022
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Lightning protection installation
- Lightning protection installation
- Lightning protection installation 06.07.2022
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- 12.07.2022
- Air Con in each room
- Air Con in each room
- Air Con in each room
- Air Con in each room
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Aesthetic work completion process
- Pool Treatment
- Pool Treatment
- Pool Treatment
- Glass railing on the top floor
- Glass railing on the top floor
- Glass railing on the top floor
- Glass railing on the top floor
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Evening vibes 08.08.2022
- Agung Eka Putra (Builder)